1. The hydraulic oil on the saw shall be filled and a layer of oil shall be applied to the sliding and rotating parts.
2, the belt saw machine installed saw band, adjust the tension device(turn saw frame left handle) so that the saw band up tight to an appropriate degree, at the same time adjust the trip switch contact just hit the iron, in the open state.
Add enough coolant to the cooling tank.
4. After the above preparation work, connect the power supply, ground must be standard and reliable, turn on the power switch(in the electrical control box), start the saw test car, according to the sign indicated in the rotary correction wiring, and listen for the sound is normal. During operation, let the saw bow drop automatically, so that the saw band down to less than the workbench 0.5 ~ 1mm, the limit switch head against the impact block automatically rises, when reaching the limit position, whether automatic stop, three consecutive experiments. In the course of operation, the adjusting tension device is in a relaxed state, so that the trip switch contact from the block power off, three consecutive experiments.

5. Check the lifting and lowering cylinder equipment, check the saw bow lift and fall, whether reliable and flexible.
6.check clamping, relax cylinder device, check clamping whether the clamping is reliable, relax flexible.
7, adjust speed adjusting knob, adjust to 1 gear(low speed) operation, then adjust to 2 gear(high speed) operation, experiment 3 times.
8.After the main motor power supply switch is turned on, the pump will start at the same time and the cooling system will run normally. Adjust the valve to check whether the coolant is flowing.
9. After doing the above preparation work, the loading material is clamped and locked, and the test saw is made.