1. To determine whether the machine is to replace the new saw blade, it can be determined in the following ways:
(1) The number of blade blade around 80 should pay attention to the machine, at any time may appear to cut the face uneven;
(2) In the course of the Silicon interception, it is also important to note whether the current is stable and, if it is above 3.3, it is possible to find the surface of the cut uneven after the cut;
(3) A new saw blade may also be used if there is an angle cut at the time the Silicon is trapped.

2. But before changing the saw blade to do some preparatory work, to change the new saw blade to pick and choose a selection of the help, tension, shovel and other tools.
3. The machine needs a new saw blade, turns off the speed of the saw blade first, turns off the cooling water, and then opens the shield. When the saw blade stops turning, it can remove the tension, rotate the screw three to five times to the left, using the U-line helper, until the alarm is turned several times to get the saw blade off.
4. When the saw blade is taken down, flush the upper and lower guide blocks with a hose to prevent the saw blade from being damaged by the Silicon slag on it. Also, wash the upper and lower roulette wheel by applying a shovel to the wheel, driving at 20-50 rpm to turn the wheel, and then use a hose wash knife to shovel the Silicon onto the wheel to flush the slag.

5. When this is done, a new saw blade can be replaced by a new saw blade, which must be attached parallel to the lower wheel. The saw blade must be attached parallel to the upper wheel but must be attached to the upper wheel in the order of 1-2 mm. After that, the tension must be intense, rotating to the right, and the tension must be increased to about 290-300. The speed of 50 times with a protective cover will make the saw blade turn and the cooling water will be placed on the pipe. At this point tension will drop, then add tension tension to around 290-300,(why add tension twice? Because when the saw blade turns, the saw blade is a little bit active. )The current is about 2.4, the normal range of 0.1 is stable, at 200, see if the blade has any signs of concatenation, you can speed up if you do not, and slowly increase the speed of the new blade, the first few blades must be 750, otherwise the saw blade around 50-70, there is likely to be a bad effect, thus shortening the blade's life. This leads to excessive use of new saw blades, resulting in less waste than desired.

6. Hold a Silicon anchor without cutting off an 8 mm scrap layer on the machine and then move slowly like a left push near the baffle to see if the line is aligned with the saw blade or the lowest scrap layer on the chip is raised(at times the lowest scrap layer is not 8 mm) whereas the lowest scrap layer is lowered when the scrap layer is not noted when it is finished. Stuck saw blade causing alarm damage saw blade.

7. Click to enter the servo control panel to manually move the workbench towards the saw blade. When the distance from the saw blade is about 1mm, click the zero point position to make this position the beginning of each silicon chip cut.
8. When the zero point position is set, click on the isometric cutting control panel to enter the adjusting cutting speed of 3-10 mm / min, click on the cutting control panel to enter, and click on two automatic ways to cut the first knife.